Today was our last day on site. We managed to get all of the piping for the wetland placed and connected. So basically all of the piping is in from the edge of the proposed pad location to the end of the infiltration gallery. The inlet and outlet of the wetland has been backfilled with the large gravel (completely covering the collection and outlet pipes). Approximately one foot of small gravel has backfilled in what will be the wetland bed itself (this is the area the reeds will need to be planted in). We did not want to completely backfill the wetlands because it would be extremely difficult down the road to dig through 2 feet of small gravel to plant the reeds (the reeds need to be planted after the station is up and running otherwise they will die).
Since we did not have a translator, we called a friend back home that speaks Telagu so that he could inform the villagers that today was our last day. We also told them that Mike would be coming to finish up the project, so they are expecting him on the 9th or 10th. It is unfortunate that we could not communicate with the villagers over the course of the project. Not only would we have liked to tell them about the project and provide education about water quality and maintenance of the facility, but also to get to know them and learn more about their lives. They were very kind people and I can only hope that this project makes their lives better at least in some small way.
The villagers gave us beautiful flower lays (spelling?) upon our departure. It was a bittersweet departure as we would have liked to see the project through to completion; however, at the same time this has been an exhausting experience.
Tonight we take the train to Hyderabad.
Saturday, March 8, 2008
Friday, March 7, 2008
Day 18, Thursday March 6
Today was an exhausting day. It is a holiday here in India, and one that is especially celebrated down here in Andhra Pradesh. That being said, it made us feel somewhat guilty having the villagers work all day, as we needed their help to trench and get the piping ready for the plumber to make his connections. In the end, it was a long day, but we did it! All of the piping is cut and ready for the plumber to connect tomorrow. We also had a mason on site to install the precast concrete rings that we will be using for the settling basin (at the inlet of the wetland) and the valve pit (for the ball valve at the outlet of the wetland). The mason also needed to install some steel mesh and concrete to give the rings a bottom. He also made holes in the precast rings for the necessary piping.
Tomorrow we will work on backfilling the wetlands. We will try to accomplish as much as possible as it is our last work day in the village.
Tomorrow we will work on backfilling the wetlands. We will try to accomplish as much as possible as it is our last work day in the village.
Wednesday, March 5, 2008
Day 17 - Wednesday March 5
First of all, I just wanted to say thanks to the folks at EBMUD for all your support - it is so nice to see all of your supportive comments when I am feeling down. Special thanks to Mitch for all your comments, not to mention that special delivery that you sent me via Dave C. before I left. Also, you are awesome for looking up UPVC specs - seriously, I could use your expertise on all this stuff here :).
So today was a pretty busy day. This morning we got the Silpaulin that will be the wetland liner. We spent the first part of the day trying to level the wetland and ensure that it sloped in the correct direction, which was no mean feat as we don't have alot of equipment. So we spent over an hour surveying the wetland, and then figured out where we needed to dig. Again, since we don't have a translator, it was very difficult to try to tell the villagers what we wanted them to do (and why we were doing it). So we figured the best way to do it was to show them. So we started digging and smoothing out the area. The villagers caught on pretty quickly, and promptly took the shovel out of my hands. Once we got the ground sloped correctly, we put down the PVC liner. We spent the rest of the afternoon putting down the first layer of soil, and then starting the 2 foot berm around the perimeter of the wetland. This took quite some time as the villagers carried the rocks to us one plate full at a time. After several hours, everyone was too hot to continue and we halted work for the day. Tomorrow we plan to head out to the village very early to complete the berm and install the first layer of gravel for the inlet and outlet areas.
So today was a pretty busy day. This morning we got the Silpaulin that will be the wetland liner. We spent the first part of the day trying to level the wetland and ensure that it sloped in the correct direction, which was no mean feat as we don't have alot of equipment. So we spent over an hour surveying the wetland, and then figured out where we needed to dig. Again, since we don't have a translator, it was very difficult to try to tell the villagers what we wanted them to do (and why we were doing it). So we figured the best way to do it was to show them. So we started digging and smoothing out the area. The villagers caught on pretty quickly, and promptly took the shovel out of my hands. Once we got the ground sloped correctly, we put down the PVC liner. We spent the rest of the afternoon putting down the first layer of soil, and then starting the 2 foot berm around the perimeter of the wetland. This took quite some time as the villagers carried the rocks to us one plate full at a time. After several hours, everyone was too hot to continue and we halted work for the day. Tomorrow we plan to head out to the village very early to complete the berm and install the first layer of gravel for the inlet and outlet areas.
Tuesday, March 4, 2008
Day 16 - Tuesday, March 4
Today we received approval to buy the piping for the wetlands. We spent a good part of the day finding out more about the various grades of PVC (in India there are numerous grades of PVC including UPVC, CPVC, regular PVC, etc), and there are not really stringent standards in place to ensure that pipe manufacturers adhere to government standards for pipe production. Of course, our first concern is that we use a pipe that is non-toxic and also will be relatively durable. We had originally intended to use UPVC, however, it was relatively costly and we did not receive permission to make this purchase. By 5 pm, we were given the approval to purchase Finolex PVC pipe, which we were ensured adhered to IS:4985, which is the standard for drinking water applications.
So unfortunately we did not head out to the site today as we were waiting on materials. Tomorrow we plan to head to the site first thing to start grading the wetland and laying down the liner.
So unfortunately we did not head out to the site today as we were waiting on materials. Tomorrow we plan to head to the site first thing to start grading the wetland and laying down the liner.
Monday, March 3, 2008
Day 15 - Monday, March 3
Today the excavation of the wetland continued. We laid out the location of both the settling tank and the drain and infiltration pipes. The villagers volunteered to trench for the infiltration pipeline in the afternoon. We are now awaiting the rest of our materials (silpaulin for the wetland liner and the associated piping) before work can continue.
Sunday, March 2, 2008
Day 14 - Sunday March 2
Today we went to the village in the morning to lay out the wetland area. The villagers helped us clear the area (there were bushes, sticks and random other debris in the proposed location). The laborers came later in the day and began the excavation. The excavation for the main body of the wetland was started today. The excavation for the settling tank and the trenching for the infiltration pipe will probably occur tomorrow.
Saturday, March 1, 2008
Day 13 - Saturday March 1
We received approval from the Rotary contact for the slightly larger pad size and the second bore well, which is great news as both were required to make the project successful.
In the morning, the villagers installed a second bore well on the opposite end of the proposed pad. Once the contractor's workers arrived on scene, they promptly began pouring the second half of the columns. We verified that they were level and of the correct dimensions, though the workers were also double checking the dimensions themselves with plum bobs and a piece of flexible tubing. Both the villagers and the workers were also ensuring that the pours were being kept wet. The original plan was to install the roof after the columns were installed; however, the decision was made to hold off on the installation of the roof until Mike arrives on March 8, as he would like to oversee this operation (Mike contributed to the design of the structure). We were informed of the decision during the day and it was a bit of a shock as we were not consulted during the decision making process. So the next step of the construction will involve the installation of the wetland. We are still trying to find a place where we can buy reeds; however, the language barrier is pretty extensive and I do not think people are understanding what we need. We have been to several nurseries with no luck in finding the plants we will need for the wetland. If worst comes to worst, we may need to simply have the villagers or the workers go down to the Buckingham Canal and pull out some of the naturally occurring reeds for our project.
Since the wetland construction is about to begin, we scouted the area for the best location for it. There were two acceptable areas, but unfortunately one is the site of a future road. That made the decision quite easy regarding the final placement of the wetland. We plan to arrive at the site tomorrow first thing in the morning to lay out the dimensions for the wetland. The contractor's workers will then start the excavation.
In the morning, the villagers installed a second bore well on the opposite end of the proposed pad. Once the contractor's workers arrived on scene, they promptly began pouring the second half of the columns. We verified that they were level and of the correct dimensions, though the workers were also double checking the dimensions themselves with plum bobs and a piece of flexible tubing. Both the villagers and the workers were also ensuring that the pours were being kept wet. The original plan was to install the roof after the columns were installed; however, the decision was made to hold off on the installation of the roof until Mike arrives on March 8, as he would like to oversee this operation (Mike contributed to the design of the structure). We were informed of the decision during the day and it was a bit of a shock as we were not consulted during the decision making process. So the next step of the construction will involve the installation of the wetland. We are still trying to find a place where we can buy reeds; however, the language barrier is pretty extensive and I do not think people are understanding what we need. We have been to several nurseries with no luck in finding the plants we will need for the wetland. If worst comes to worst, we may need to simply have the villagers or the workers go down to the Buckingham Canal and pull out some of the naturally occurring reeds for our project.
Since the wetland construction is about to begin, we scouted the area for the best location for it. There were two acceptable areas, but unfortunately one is the site of a future road. That made the decision quite easy regarding the final placement of the wetland. We plan to arrive at the site tomorrow first thing in the morning to lay out the dimensions for the wetland. The contractor's workers will then start the excavation.